Case Studies - Equipment

LPA Screen Maintenance Resolves SCR Ash Piling and Pluggage

Introduction A 2,000MW pulverized coal-fired power plant in the Midwestern United States, historically suffered from severe ash piling and pluggage in its SCR, forcing derates in as little as three months of operation. In 2017, IGS was awarded a project...

The Problem: A History of Screen Breaches

This unit had proven to be a very difficult application for LPA screens, as two different designs had been attempted previously, with little success, which resulted in screen breaches between outages and extensive LPA accumulation in the SCR.

LPA Screen Installation

The IGS NoNOx LPA screen was installed in 2017, replacing the previous OEM design. The superior design and protective High Velocity Thermal Spray (HVTS) cladding proved successful in this aggressive application, with no reported screen breaches between outages. This provided reliable LPA filtration and protected the SCR. This, along with the SCR air cannons and CatFlow® screens, addressed the SCR ash piling and eliminated SCR related outages and derates.

Ensuring Long-term LPA Screen Reliability

However, similar to brake pads on a car, the LPA screen system does require periodic maintenance to provide long-term performance. During an inspection in early 2023, although no breaches in the LPA screens were found, it was determined that the LPA screens were showing signs of wear, and action would be required to extend their service life and ensure long-term reliability.

The Solution

IGS reviewed the various maintenance options with the plant, and it was decided that a partial screen panel replacement and full system refurbishment was the most cost-effective solution to keep the system in a reliable condition.

The refurbishment process involved media-blasting the LPA screen, which allowed for a detailed inspection of each screen panel while simultaneously preparing the screens for the refurbishment coating application. IGS then inspected the panels closely, looking for indications of severe wear and damage that would require replacement. Worn out panels totalled roughly 20% of the screen panels, which were replaced with new NoNOx LPA screen panels.

 

A Dual-purpose Coating Application After these panels were replaced, IGS reapplied the two-stage topcoat to the remainder of the LPA screen array. This coating is dual purpose; it adds a layer of erosion protection while the bright green color of...

The Result

The refurbishment of the LPA screen ensured it would continue to offer reliable protection of the SCR for years to come, while also avoiding a full LPA screen panel replacement. This provided significant cost savings.

Additionally, the refurbished top coat made future inspections quick and easy by making the green pigment a wear indicator. An inspector can now assess and monitor the LPA screen condition quickly and regularly, ensuring proper maintenance and eliminating the potential for LPA screen failures.

Conclusion Proactive maintenance programs can significantly extend the life of the LPA screens, drastically reducing replacement costs. Ensuring LPA screen reliability is the first and most important step in keeping an SCR reactor free from build-up. In a volatile economy...
I’m here to help Andrew Kline IGS Subject Matter Expert
Related Case Studies: Methane Reformer SCR Fouling no Longer a Costly Problem SCR Fouling Solved; Production Derates Eliminated LPA screen maintenance and replacement at US coal-fired power plant SCR Catalyst Pluggage Threatens Environmental Compliance at Power Plant
Related Questions: What other SCR efficiency solutions do you provide? How can you clean SCR screens online? Why is LPA screen maintenance important?
Related Services: Fine Particle Screens Air Cannons Ceramic Refractory Coating CatFlow® Screens Hot Vacuum Service

SCR Catalyst Pluggage Threatens Environmental Compliance at Power Plant

Introduction In 2021, it was discovered that a 650MW pulverized coal-fired power plant on the mid-Atlantic east coast was experiencing severe pluggage and fly ash build-up on its SCR catalyst, resulting in environmental compliance issues. Upon closer inspection, Large Particle...

The Problem: Catalyst Screen Erosion

Fly ash accumulated leading to further flow disruption and extreme erosion of the catalyst. It was found that the existing LPA screens were in disrepair due to poor design and neglected maintenance, resulting in significant LPA bypass to the SCR. These screens comprised mostly of wire mesh sheets constantly eroded away between outages and allowed large volumes of LPA to pass through.

Popcorn Ash Build-up

This LPA was littered across the first and second catalyst layer, resulting in the flue gas flow being forced through less than half of the designed area. Over time, the resulting catalyst pluggage became so severe that large portions of the catalyst completely eroded away. The damage to the catalyst on layer 1 was beyond repair and attempting to clean the modules was not a viable option.

Action Required to Remain Environmentally Compliant

It became evident that to meet environmental compliance, drastic improvement was required. The situation was so severe there was concern that it would not be economically viable to restore the system, which threatened to shut the unit down permanently, well before its planned retirement date.

The Solution

Due to the remaining life expectancy of the plant, a full system overhaul was not economically viable. However, to save the operation of the unit, three things were clear. The first layer of the SCR catalyst had to be replaced, LPA had to be prevented from reaching the SCR, and the remaining layers had to be cleaned and restored.

Restoring DeNOx Performance

To save the unit and keep the project within a reasonable budget, IGS worked with the plant to devise a hybrid retrofit of the LPA screen, focusing on upgrading the highest risk screen regions.

To restore the DeNOx performance and improve the ash handling capacity of the SCR, the first catalyst layer was replaced with a hybrid layer of DustBuster and a standard honeycomb catalyst, all of which was retrofitted with IGS CatFlow® screens. The screens help to reduce the fly ash accumulation while also providing a last line of defense against combustion and non-combustion LPA.

Lastly, the lower layers of the SCR were cleaned using dry ice blasting and vacuuming. Although the first layer provides the bulk of catalyst potential, restoration of the lower layers was critical to allow the unit to reach its designated end of life, near 2030.

This combined approached proved by working with experienced SCR experts, it was possible to bring the unit back to compliance within a reasonable operating budget.

The Result and Inspection In 2022, a follow-up inspection was performed to assess the effectiveness of the upgraded LPA screens and SCR system. The NoNOx LPA screens had successfully prevented LPA from reaching the SCR, resulting in minimal fly ash...
I’m here to help Andrew Kline IGS Subject Matter Expert
Related Case Studies: Methane Reformer SCR Fouling no Longer a Costly Problem SCR Fouling Solved; Production Derates Eliminated LPA Screen Maintenance Resolves SCR Ash Piling and Pluggage LPA screen maintenance and replacement at US coal-fired power plant
Related Questions: What other SCR efficiency solutions do you provide? How can you clean SCR screens online? Why is LPA screen maintenance important?
Related Services: Fine Particle Screens Air Cannons Ceramic Refractory Coating CatFlow® Screens Hot Vacuum Service

LPA screen maintenance and replacement at US coal-fired power plant

Introduction In 2010, IGS installed an LPA screen system in each of the four 700MW boilers in a pulverized coal-fired power plant in southeast US to protect the newly installed SCR from LPA, commonly known as popcorn ash. If allowed...

Proactive Maintenance is Key

The facility chose to invest in a high-quality, long-lasting, and reliable NoNOx LPA screen system to protect the SCR. Other than regular inspections, very little maintenance was required for the first six years of operation. However, similar to high-performance brake pads on a heavy-duty truck, even the best LPA screens wear over time and eventually require routine maintenance and replacement. Screen breaches (as shown in the image) aren’t uncommon but can be costly.

The Solution

Understanding the importance of keeping the SCR free from LPA, this plant adopted a proactive maintenance approach. This involved regular detailed inspections of the system and documentation of wear patterns found on the screen. If a screen panel was found to have significant erosion (shown in the image), it was replaced with spare panels held onsite prior to screen failure, eliminating the risk of LPA screen breaches between outages.

LPA Installation

By 2022, the LPA screen system had reached the end of its expected service life. Although the panels were in relatively good shape for their age, the plant decided to fully replace the LPA screen panel array, to ensure reliable LPA filtration for years to come. The plant also decided to upgrade the system to the two-stage LPA screen coating, which offers better erosion protection and a green visual wear indicator. This visual wear indicator dramatically reduces inspection time while allow improving inspection accuracy.

The Result The exceptional maintenance practices implemented by the plant resulted in hassle-free LPA screen operation and complete protection of the SCR from LPA and related ash build-up. By performing regular inspections and utilizing a proactive maintenance approach, this plant...
I’m here to help Andrew Kline IGS Subject Matter Expert
Related Case Studies: Methane Reformer SCR Fouling no Longer a Costly Problem SCR Fouling Solved; Production Derates Eliminated SCR Catalyst Pluggage Threatens Environmental Compliance at Power Plant LPA Screen Maintenance Resolves SCR Ash Piling and Pluggage
Related Questions: What other SCR efficiency solutions do you provide? How can you clean SCR screens online? Why is LPA screen maintenance important?
Related Services: Fine Particle Screens Air Cannons Ceramic Refractory Coating CatFlow® Screens Hot Vacuum Service

Pioneering Carbon Capture and Storage Project Back on Track with Rapid Mobilization

Carbon Capture and Storage Project A multinational investment company and an American energy corporation have embarked on constructing a ground-breaking direct air capture facility in the US Gulf Coast region. Their primary objective is to capture carbon directly from the...

Fabrication Oversight Requires Emergency Response

The stakeholders encountered a critical change of metallurgy. The vessel had a particular coating specification that required further review. This coating would have proved inadequate for the pure oxygen environment and temperature ranges required. This was compounded by the unique vertical construction of the process stream structure, requiring timely sequential assembly of its segments.

Fast Mobilization and Material Selection The project timeline was at stake, with over 100 workers on-site unable to proceed until the issue was addressed. Each day of delay was costing over $500k. The engineering team behind the project has contacted...
Strategic Decision-Making With a verbal agreement secured, after both technical and commercial approval, the IGS team swiftly moved into execution mode. The urgency stemmed from the sequential nature of the equipment’s construction, where each segment completion was contingent on the...
Two-Part Execution IGS execution strategy involved a two-staged work approach. The initial mobilization started on the 27th of December 2023 until the 2nd of January 2024 and focused on addressing critical work areas around internal piping systems. Working through the...
Challenges and Innovations The vessel, comprising two sections, required precision HVTS Technology. The spray-ability and speed of HVTS execution proved crucial in addressing complex areas, where traditional welding would have been impractical.

Project Impact and Future Prospects

The successful and expedited completion of the project averted significant weeks of lost time for all stakeholders involved on the project. The project and HVTS execution emphasized the critical role this played in keeping the project on schedule and served as a testament to the quick decision making of the project managers. IGS’ operations excellence played a key role in turning this emergent work into a success story in the Carbon Capture market.

How can IGS’ HVTS Services deliver value? I’m here to help JanAlbert Schutte IGS Subject Matter Expert
Related Case Studies: IGS Facilitates Significant Reduction in Emissions at Utility Plant ½ The Cost and ⅓ The Application Time in LP Separator Renewables Conversion Welding Alternative Achieves 50% Savings in Renewables Conversion
Related Questions: What is high velocity thermal spray? How does corrosion in carbon capture and storage occur? How to stop corrosion in CCS projects?
On-site Thermal Spray Coating Services from IGS: High Velocity Thermal Spray (HVTS) IGS TUFFss ONLINE TSA Metalspray® Hexavalent Chromium Filter System: IGS ClearStream

Proactive CFB Boiler Maintenance Saves $ Millions and Triples Run Cycles

CFB Boiler Protected with IGS SMARTGard® This coal-burning boiler was commissioned in 1998 with an 11,450 sqft (1064 sq.m.) heating surface and 1.2 million pounds per hour (544 t/h) steaming cap. IGS first applied HVTS in 2020 and monitored the...
PROBLEM: The annual cost from forced outages, RIK, general maintenance and electrical cost associated with each unit could reach an average of 8-12 Million dollars. SOLUTION: IGS SMARTGard® addressed the problems and increased the run cycles from 4-6 months to...
1. Before IGS SMARTGard® See the bare tube condition prior to the IGS SMARTGard® HVTS application. Notice hard edges around discontinuity from erosion damage where ash build-up has deviated material flow into the unprotected substrate.  
2. IGS HVTS Applied In order to prevent further substrate wastage IGS has cladded the area with HVTS as opposed to having to cut and replace tubes. Pictured is the area of low tube thickness now protected by IGS cladding....
3. Ceramic Top Coat Once the cladding process has been completed, IGS applies a proprietary ceramic top coat as a wear indicator during future outage inspections to help navigate future coating plans.  
4. After a 14-Month Run Cycle The coated area after a 14-month run cycle appears on the right. The presence of ceramic top coat (Green) can still be identified meaning underlying thermal spray cladding is still at 100% as-applied condition....
The Benefits of SMARTGard® HVTS cladding reduces tube wear and increases overall production. This reduces costs associated with maintenance from both planned maintenance and forced outages. Reducing the need for welding and eliminating the requirement for refractory in some areas...
I’m here to help Colin Bateman IGS Subject Matter Expert

SMARTGard®: Weld Overlay Alternative for Boiler Pressure Parts

A waste-to-energy plant in Turin, Italy, was preparing for an outage on one of their lines. They were waiting for approval from the notified body to carry out the weld overlay. The outage was nearing, and the approval was yet...
Power Plant
Corrosion of the Boiler Pressure Parts The plant, built by CNIM, was commissioned in 2014. Following several years in operation, they noticed corrosion in the second pass of the boiler. Alloy 625 weld overlay has already been installed in the...
Selecting a Suitable Solution IGS SMARTGard® HVTS was selected for several reasons. Strong global references in similar applications supported by laboratory testing. HVTS is not a welding process – the pressure part temperature stays below 150C during the application, therefore,...

Plant Replaces Weld Overlay in its CFB Boiler

This CFB boiler built in the mid-1990s is designed to burn anthracite coal, hazardous waste coal piles located throughout Pennsylvania. The plant observed severe erosion and metal wastage on the boiler tube due to how these combustors operate. Over the...

SMARTGard® Thermal Spray Stops Alloy T24 Fireside Corrosion in Supercritical Boiler

This Power Plant provides steam to nearby industrial facilities using sustainable biomass (such as SBP, GGL, FSC, and PEFC) and industrial by-products (such as bio-propane) to generate power and heat.
SUPERCRITICAL BOILER The boiler has five rows of six burners on two sides. These burners are fed with coal, bio-propane, wood, and MBM (Meat and Bone Meal) – animal residue foam injected into the boiler. MBM is very erosive, so...
A SUPER ALLOY T24 BOILER The unique feature of this boiler is that it is one of the first boilers manufactured with alloy T24. T24 material is a novel superalloy, designed for strength at high temperatures that does not require...
ALLOY T24 WELDING ISSUES Welding this superalloy is difficult, especially without annealing or post-weld heat treatment. Non-alloy steel, a material used to produce typical boiler tubes, PH 265GH, is the easiest material to weld. The superheater material, 10CrMo9-10, is known...
As a result, these first boilers manufactured with T24 suffered many leaks after just a few hundred hours of operation. Welding experts from VGA and other parties involved helped them find the solution, enabling them to erect such supercritical boilers...
TESTING HVTS SUPERALLOY PROTECTION As the plant continued having multiple stoppages due to tube leaks, in 2019, they decided to apply a protective cladding onto a test area to evaluate its performance. IGS SMARTGard® HVTS was chosen for this on-site...
SMARTGard®: IGS HVTS – High-Velocity Thermal Spray HVTS cladding was also applied onto superheater hanging tubes facing soot blowers. Test areas were installed onto various locations of tube bundles as an alternative to thick metal protection shields.
A LEAK OCCURRED DURING HVTS TESTING After installing the trial HVTS application in August 2019, another forced unexpected shutdown due to a tube leak occurred in December that year. Although initially it was suspected to be in the IGS clad...
QUALITY INSPECTION PROGRAMME UT Quality inspected HVTS cladding and unprotected tubes. They performed tube scanning using a PEC Scan, Pulsed Eddy Current scanning, that delivers specific tube thickness mapping. This inspection was conducted in 2019 and again in 2021. By...
INSPECTION DISCREPANCIES AND RESULTS When comparing inspection results between 2019 and 2021, the inspection company immediately noticed that some areas appeared to have gained thickness. Cyril Narjoz, IGS Boiler Reliability Expert, commented:
“You need to keep in mind that first of all, you never read the same point two years later, it’s impossible. Even when you do the reading on the same spot, during the same inspection or the day later, you...
The inspection results were matched with the positioning of the HVTS cladded area. It was a challenge because it didn’t match the red area or the colored area of the thinning. Moreover, to make it a little more complicated, in...
“Nevertheless, what we can see in the area where we applied the HVTS the cladding, there’s much less thinning. And above the area, we have this red zone where we can notice up to nearly one millimeter per year loss...
FUTURE-PROOFING THE BOILER Initially, prior to evaluating the readings, the plant had commissioned IGS to expand their HVTS cladding scope to protect a 35 m² surface area finishing the band and protecting a band below. However, after evaluating the readings...
HVTS APPLICATION IN 2021 The expanded scope was completed in record time by IGS utilizing additional operational resources to speed up the process, with work proceeding simultaneously on several levels. Plant representative said: “We really appreciated IGS’ flexibility during the...
SUPERHEATER TUBES This project’s second exciting part included the hanging superheater tube bundle with steam at 320 bar / 5400C. These tubes face the soot blowers that are operated at regular intervals to clean deposits of the tube surfaces. Welded...
Cyril Narjoz commented: “Cladding supplied by a different vendor was also applied and tested in a similar area and performed well.  The key difference is – these other tests were sprayed in the workshop before being installed in the boiler....
CONCLUSION As T24 material is extremely challenging to weld. One of the major benefits of the IGS HVTS solution is that no welding is involved in its application. Since HVTS is not welded, it does not generate any alteration to...
I’m here to help Colin Bateman IGS Subject Matter Expert